Integrated blocks for launch of girders in Kalyan-Karjat section | Mumbai News


Integrated blocks for launch of girders in Kalyan-Karjat section

MUMBAI: The Central Railway carried out an integrated block on CSMT-Kalyan and Kalyan-Karjat section from late Saturday night till wee hours of Sunday for launching of girders, a senior official said.
The traffic and power blocks involved Up and Down slow and fast lines, 5th & 6th lines on CSMT-Kalyan and Kalyan-Karjat section. This integrated block will be carried out late Sunday night and till wee hours of Monday as well, the official said.
The block was for launching girders for 3rd new Patripul Road Over Bridge (ROB) between Thakurli and Kalyan stations, 12 mts wide Foot Over Bridge (FOB) at Ulhasnagar, ROB in lieu of Level Crossing (LC) Gate between Kalyan and Ambarnath, and 6 metres wide FOB at Neral.
The traffic block impacted Dombivli-Kalyan Up & Down lines, Kalyan-Ambernath Up and Down lines and the 5th and 6th lines of Central Railway, the official said, adding that some of the Mail and Express trains were diverted during the blocks.